cost management - project schedule
Your boss is worried about the project schedule. There is a critical deliverable due to the federal government in 2 weeks. If you miss the deliverable, you could lose the entire contract. To help reduce the boss's stress you show him teh earned value calculations you just completed. They show your cost performance index CPI is 1.25, your actual cost AC is $400 million and your planned value PV is $490 million. Should your boss be comfortable?
A)Yes, your SV is $10 milliion
B)No your CPI is too high
C)He needs more data