A project is over budget to date. Which of the following is not a reason this could have occured?
A)More work than planned was accomplished
(B)There was a cost increase from the supplier
C)Work was delayed
D)Work was done inefficiently
Answer is given as ( C ). Why can't it be ( B )??
Can someone explain?