cost management - type of estimate

 When a company is unsure about the cost of the project but needs to have the project accomplished, which of the following estimating methods might the company rely upon?

A) Parametric          B) Analogous             C) Bottom-Up      D)Vendor bid analysis

 

The answer is given as D) Vendor bid analysis

Why can’t the answer be Analogous?