Does Verify scope decides the phase exit criteria completion ?
Submitted by Renji2013 on Fri, 03/29/2013 - 07:18
Forums:
Interesting pmp questions which I cannot find right answer.
Q1. Sebastian is a project manager in charge of an R&D project. The project has completed phase 1 and is moving into the next phase of the
project. What is the process he has to plan for, to ensure that the project requirements have been met in phase 1
and the project can move to the next phase?
a. Verify Scope
b. Close project or Phase
c. Nothing to do
d. Quality Contol