PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

cost management - EVA

 For the purpose of Earned Value Analysis (EVA), Joe decides to count a task 50% complete when any work has been done on the task. The task will be considered 100% complete when it is finished. Joe is using which of the following rules to indicate progress on a task?

A) 50-50 rule    B) 0-100 rule   C)0-50-100 rule  D) 80-20 rule

 

Answer is given as A) 50-50 rule