cost management -- new duration
Submitted by vijayavadrevu on Fri, 03/29/2013 - 03:37
Forums:
Using the data shown below, the new duration of the project is:
PV = $4,000, EV = $ 6,000, AC = $8,000, BAC = $12,000, Critical path = 15 weeks
Answer is given as 10 weeks
Can someone explain the concept?