Question related to Human Resource Management +PM Prepcast

Question: You are in the executing phase of your project. You have spent a lot of time negotiating for the best human resources but the people you have obtained do not have the expertise necessary to complete the project activities, according to the Project Management Plan. What is the first thing you should do to try to remedy this situation?

Options

A) Update the Human Resource Management Plan

B) Issue a change request

C) Renegotiate for the required human resources

D) Provide training to the under-skilled human resources

----