Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Initiation question from Scordo book

Linda is a project manager in charge of an online banking project. The project has completed phase 1 and is moving into the next phase of the project. Which of the following processes must be carried out first for the phase 2?
Define Scope
Identify Stakeholders
Develop Project Charter
Develop Project Management Plan

He said that the answer is identify stakeholders! Shouldn't it be develope the charter?!