question on risk - avoid vs mitigate
here is a question that i would need advices
Q146
In your project, you want to extend the project schedule to reduce the threat that your project may not get the resources in time to complete the project. This is an example of.
1 ) develop schedule
2 ) Avoid risk
3 ) Mitigate risk
4 ) Secondary risk
Ans is 2
Pmbok def :
Risk avoidance involve changing plan to eliminate the threat. This include extending the schedule, changing the strategy or reducing scope
Vs