question - on conduct procurement
Submitted by philzs on Sun, 04/12/2015 - 02:23
Forums:
pmstudy e4q120
i got a weird question from pmstudy
Which of the following should you(buyer) pay attention when you conduct procurement?
1 ensure that contractual obligation are met
2 apply project management
3 monitor payment to seller
4 perform regular procurement audit
ans : 4
no idea why its answer 4 as procurement audit is in close procurement
anyone?