Resource leveling vs Critical chain method
Submitted by philzs on Mon, 03/23/2015 - 02:36
Forums:
10. I tought I was pretty comfortable with both terms but I got a question that asked what should you do if a resource is booked on two activities that happend at same time,
the choice was between "Critical Chain method" and "Resource Leveling"
I got the answer right, it was Resource Leveling,
But to be sure that I understand everything I went back to Rita and I read that
Resource leveling = deal with a limited amount of resources,