Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Resource leveling vs Critical chain method

10. I tought I was pretty comfortable with both terms but I got a question that asked what should you do if a resource is booked on two activities that happend at same time,

the choice was between "Critical Chain method" and "Resource Leveling"

I got the answer right, it was Resource Leveling,

But to be sure that I understand everything I went back to Rita and I read that

Resource leveling = deal with a limited amount of resources,

 

Pages