Question - Procurement vs closing

139, One way the close project or phase process differs from close procurement is

a ) procurement closure involves verification that all work and deliverables are acceptable, where close proejct or phase does not

 

b) close project or phase is only a subset of Close Procurement

C ) Procurement closure means verifying that the project is complete or terminated; close project or phase is the process of tying up all of the activities for every management process group

 