Project Selection methods Question
Submitted by eldrin.connery on Thu, 09/23/2010 - 04:01
Forums:
There are multiple projects your organization is considering for the upcoming fiscal year. Project A has an NPV of $85,000. Project B is a $1 million project and has the benefit cost ratio of 1.6. Project C has an internal rate of return (IRR) of 15%. Project D as a payback period of two years. Based on this information which is the best project to select for execution?
a. Project B
b. Project C
c. Project D
: d. Project A