Cost Management, Oliver Lehmann query.
Submitted by sam12 on Wed, 07/21/2010 - 04:24
Forums:
Hi folks,
Gotta doubt about a question from Oliver Lehmann (175q test)
Question 92.>Post-moretm analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?