Procurement Question - Most Risk To Buyer/Seller

 Here's a question I came across:

 

Which of the following contracts has the MOST risk for the buyer?

 

Cost plus fixed fee (CPFF)

Time and Materials (T&M)

Cost plus award fee (CPAF)

Fixed price (FP)

 

 

Which one do you think is the answer?  I picked the one that listed in Rita Muchaly's PMP Exam Prep (6th Edition) page 437.

 

 

 