you are in charge of a project to build a bridge across a river. You are midway through the project. However due to changes in environmental laws the project can no longer proceed and would need to terminated. Executive management has asked you to document the level of work completed for the project. This would be done in which of the processes ?

A. Project closure
B. Contract Closure
C. Project charter
D. Scope Verification

what do you think here ?