PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Here are some questions please also briefly explain

A project manager is holding a meeting with stakeholders related to the status of a large project for constructing a new runway at a major airport. The runway project has a CPI of 1.2 and an SPI of 1.25, and the manager is going to have to deliver the message to the stakeholders that a crucial quality test has failed. What kind of communication does this meeting represent?


A.  Formal verbal
B.  Informal verbal
C.  Paralingual
D.  Non-verbal

 

**********************************