Here are some questions please also briefly explain
A project manager is holding a meeting with stakeholders related to the status of a large project for constructing a new runway at a major airport. The runway project has a CPI of 1.2 and an SPI of 1.25, and the manager is going to have to deliver the message to the stakeholders that a crucial quality test has failed. What kind of communication does this meeting represent?
A. Formal verbal
B. Informal verbal
C. Paralingual
D. Non-verbal
**********************************