Float question from time management

The earliest Task C can finish is January 21, and the earliest the next task can start is January 28. From this information we can be sure that:


A.  Task C has 6 days of float
B.  Task C has 6 days of free float
C.  Task C has 7 days of free float
D.  Task C has 7 days of float

 

Please also briefly explain the choice.

Thank you all.