Sample question
Sample question: For your comments,
Project is going 1 day ahead schedule and the work is going on well. Two stakeholders just approached PM to tell that they have an improtant change that needs to be made. That change will put project behind schedule. What PM should do?
A. Implement the change because project is ahead of schedule
B. Refuse to make the change because the stakeholder did not take it to change control board
C. Refuse to make the change untill the stakeholder document it in a change request