Critical Path doubt
Submitted by jason on Fri, 08/08/2008 - 14:46
Forums:
Hi Forum,
The following is a practice question from a pmp class I attended sometime ago. I have forgotten the reason for the answer. I hope to hear what answer you would choose and why.
An AON Network diagram has these 2 critical paths :
D-E-J-L and D-E-G-I-L.
Except for activity L which has duration of 1 day, the rest have 3 days.