A scope change has been approved
Submitted by Jp2786 on Mon, 06/02/2014 - 19:35
Forums:
A scope change has been approved by the change control board which of the following MUST be impacted?
A The early start date of the activities later in the network diagram
B The cost of the project
C The expected monitory value of project risks
D The number of resources used on the project
What do you guys think?