Question of quality planning
Submitted by PMP Fighter on Wed, 06/04/2014 - 09:11
Forums:
Which of the following statements concerning quality planning is correct?
A. Quality planning should be performed regularly throughout the project.
B. Quality planning is done to compile a risk management plan.
C. Quality planning is done only during project planning.
D. Quality planning is not considered during project execution.