CPI & SPI causes
Submitted by anaz on Mon, 05/19/2014 - 06:08
Forums:
I saw this question on a mock exam and I don't agree with the answer given.
1. A manufacturing project has SPI .89 and CPI of .91. What is the best explanation why this occured?
a. Equipment purchased was more expensive than expected
b. At least one task has taken more time than expected
c. Less experience resources were used
d. Human resources used were more expensive than expected