Another Question
You are running an information security management project for "SafetyFirst" bank to protect confidential information from unauthorized access. Today you learn that a task, which is on the critical path, would take Two additional resources and Six more days to complete. Which of the following is the most desirable action in this scenario?
A.) Use Resource leveling to bring project in on time
B.) Communicate project delay to all stakeholders
C.) Change project finish date and communicate to stakeholders
D.) Meet with Sponsor