Fast Track / Crashing
Submitted by bidyutshah on Sat, 05/03/2014 - 04:46
Forums:
A Project Manager has been assigned to manage a project to develop a cheap priced laptop for a company that does not have this expertise. The project is three weeks behind schedule and under budget. After calculating the estimate at completion (EAC), the Project Manager finds that project will be $454,589 under budget, but is expected to take four weeks longer than expected. What should the Project Manager do?