Can some help me with the below questions
Submitted by Jp2786 on Tue, 04/08/2014 - 23:45
Forums:
During project executing, a project team member informs the project manager that based on her observations, the project cannot meet the quality standards set for it. The project manager meets with all the parties concerned to analyze the situation. Which part of the quality management process is the project manager involved in?
a) Perform quality assurance
b) Quality analysis
c) Perform quality control
d) Plan quality