Which of the following things must be complete before you can start ?
Which of the following things must be complete before you can start with Performing Risk Identification, Risk Analysis, and Plan Risk Responses ?
a. Plan Communications
b. Identify Stakeholders
For the Exam :
option "Plan Communications" comes before all the activities mention in the question
Option "Identify Stakeholders" is an input to all the activities mention in the question
Could anyone explain which one to choose? and why? and why not the other?