Hi all,

I've stumbled upon this question:

---
You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC?
---

I think there are two answers:
ETC = BAT - EV
ETC = 375 - 250 = 125

or...

CPI = EV/AC
CPI= 250/200 = 1.25
EAC = BAC/CPI
EAC = 375/1.25 = 300
ETC = EAC - AC
ETC = 300 - 200 = 100

What am I missing?