Scordo Time QSN - Finish to start relationship

Hi All,

I am confused with the question below. SCordo is saying correct answer is A.But my answer is B. Checke the explanation below. They are saying "The landscaping work needs to start on completion of the office building". Is that mentioned anywhere in this qsn? Instead it need to start 15 days before the completion. I am not sure this is dicussed earlier. Please Help

==============================================================

SCORDO Time QSM No 3