Sample question on EVM
Submitted by ARO on Mon, 10/14/2013 - 08:42
Forums:
Hello,
I have some difficulties with the following sample question from Rita's actual PM FASTrack test suite:
Question:
What would be the best explanation for the following: both the cost variance and schedule variance are negative, but the cost variance is lower than the schedule variance.
Correct answer according to Rita:
The project underspent because all work was not completed, but overspent for work that was done.