PMP Question1
Submitted by amyousry on Sun, 07/07/2013 - 11:25
Forums:
A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $10,000. The impact on the project brought about by these risks is estimated at $40,000. What value should be entered into the management reserve for these risks?
a. $10,000
b. $40,000
c. $0
d. $25,000