PDM Example

 


Acitvity A has a finish-to-finish relationship with Activity B. Activity A has a duration of 7 days. Activity B has a duration of 5 days with a 3 days lag. what is the total duration of Activity A & B ?


A- 12 Days.


B- 8 Days.


C- 9 Days.


D- 7 Days.


The correct answer is B , Can anyone explain why it is B ?


 