PMP Exam Question
Submitted by examsankara on Thu, 09/17/2015 - 13:16
Forums:
Hi
Yesterday I made my first attempt and failed. I have got the following problem and I don't know how to proceed with: If I recall correctly the question is:
The original plan to complete a task was 4 weeks. Engineering department added 6 weeks to complete the task. As per the organizational process assets it takes only 2 weeks to complete that task.
The following options are:
18.1
18.4
18.6
18.5