plan risk response - fall back option
Submitted by vijayavadrevu on Wed, 05/29/2013 - 15:54
Forums:
During Plan Risk Responses process, you realize that there is a critical risk which may have a high impact on the project completion. So, you create a fallback plan which could include any of the following conditions EXCEPT: