Risk Q
Submitted by Rmandal on Wed, 05/29/2013 - 17:53
Forums:
A project manager has just finished the risk response plan for a $300,000 project. Which of the follwing should he probably do next?
A. Determine the overall risk rating of the project
B. Begin to analyze the risks that show up in the project drawings.
C. Add work packages to the Work breakdown structure.
D. Hold a project risk reassessment.