shipment delay

You have received the news that your shipment of supplies will be delayed by two weeks due to bad weather. What will be your FIRST step?

  1. Fast track the project to ensure that the project schedule is not delayed.
  2. Determine how much float is available in that task.
  3. Try to get additional supplies from an alternate location as soon as possible.
  4. Take corrective action to minimize the impact of delay.