definitive estimate
Submitted by vijayavadrevu on Fri, 05/24/2013 - 10:20
Forums:
You are in the test phase of your software project, and the project sponsor has requested a definitive estimate of when your project will be completed. The most likely estimated duration is 30 days. Which of the following duration estimations will you give to your sponsor?
- 29 - 31 days
- 24 - 36 days
- 20 - 40 days
- 15 - 45 days