3 point estimate

 

  James has been managing a hotel construction project in a busy street. He is in the process of estimating activity durations for building walls and calculates the most likely estimate as 15 days. However, the work may be delayed and could take up to 18 days if less experienced construction workers are used to build the walls. But, the engineer in- charge of the work estimates the duration as 8 days when prefabricated material is used. What is the expected duration of building walls using the three-point estimate, if the engineer's estimation is assumed correct?