EV questions
Submitted by cnppmp on Mon, 05/20/2013 - 16:37
Forums:
Q1) A task was scheduled to use two persons, full time, and take two weeks to complete. Instead, the project manager was only able to assign one person to this task. At the end of two weeks, the person assigned to the task completed 75% of the work.
What is the cost performance index?