priority and urgency
You are working as project manager in an Aerospace Firm and you are currently given in charge of manufacturing a new technology airplane which can cover 1500KM per hour. You are currently updating your risk register and adding priority and urgency values to the risk. You find two risks Risk A with Medium Priority ,High Urgency and Risk B with High Priority and Low Urgency. Which of the above risks you should take care first?
A) Risk B
B)Risk A
C)both should be given equal precedence
D)None of the above