ETC Q
Submitted by crushPMP on Wed, 05/15/2013 - 03:43
Forums:
As a project manager, you have selected Project A that has an initial budget of $1,000 out of which $800 has already been spent. To complete this project, you need an additional $500. Project B will require $1,200 only for completion. Which project would you prefer to manage and what will be its ETC?