PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Present value

 An upgrade of your company's  financial system is estimated to save your department $10,000 in the first year, $30,000 in the second year and $75,000 in the 3rd year. The cost to upgrade the system is $150,000 and is expected to take 15 months to implement . Given this data, what is the approximate present value (PV) of this project?

A)$95,000

B)$102,000

C)$132,000

D)$252,000

 

Can someone help in solving the problem? What should be r, rate of interest