Free PMP Exam Sample Question
The following PMP® exam sample question is taken from the Free PMP Exam Simulator:
------------------------------
You developed alternative schedules based on the best-case and worst-case scenarios in your project. You want to keep these alternative schedules stored in your project, in case of changes in project resources. Where would you store alternative schedules?
a) Schedule Baseline
b) Schedule Data
c) Project Documents
d) Project scope statement
------------------------------