Question related to SV calculation

Hello

Please help me understand how to calculate the PV for determining the SV for answering the below question.

You are a project manager who is in charge of a technical documentation project. The project is 30% complete after 2 months and has cost $53,000. The budget for the project is $90,000 and is scheduled to last 6 months. How is the project performing?