Question related to Close Process - PMP - Correct order of action
Submitted by hemald on Thu, 08/20/2015 - 04:25
Forums:
Which of the following is the correct order of actions that you take during the closing processes?
1) Get formal acceptance, release the team, write lessons learned, close the contract
2) Write lessons learned, release the team, get formal acceptance, close the contract
3) Get formal acceptance, write lessons learned, hand over deliverable to stakeholder(s), close the contract
4) Get formal acceptance, close the contract, write lessons learned, release the team