performance metric
You are managing a project to update all corporate computers with a software patch. The budget for this entire project is $25,000. But as this task is executed, you realize that installing the patch on certain computers is more complex and time consuming than expected. This has resulted in increased costs. Which performance metric can clearly indicate this situation of overspending?
A) Schedule variance
B)Cost variance
C)Actual cost
D)Variance at completion