PMP / CAPM exam Question bank

Want help on questions?. You can post here or you can post sample questions. Anything related to PMP questions go here.

Q. change to the critical path

 The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the BEST thing for the project manager to do?

A. Compress the schedule to recover the two weeks

B. Cut scope to recover the two weeks

C. Consult with the sponsor about options

D. Advise the client of the impact of the change

 

Shouldn't customer and sponsor be the same person in this question? Which answer you think is more correct?

Pages