Q. Integration
Submitted by y0zh on Thu, 05/09/2013 - 13:04
Forums:
you are taking over a project during project planning and discover that six individuals have signed the project charter. Which of the following should MOST concern you?
A. Who will be a member of the CCB
B. Spending more time on configuration management
C. Getting a single project sponsor
D. Determining the reporting structure
Can somebody please explain me with reference in PMBOK the correct answer?