contracts MOST risk for the Buyer
Submitted by chidambararaj1 on Mon, 07/22/2013 - 18:47
Forums:
Which of the following contracts has the MOST risk for the Buyer
A. Cost plus fixed fee (CPFF)
B. Time and Materials (T&M)
C. Cost plus award fee (CPAF)
D. Fixed price (FP)
As per head first it is T&M. But I choose CPFF. Rita and PMBOK also says the same
Can anyone explain this?