wht do you think on this Risk ?
Submitted by akkarthik on Mon, 07/22/2013 - 12:06
Forums:
You are managing a chain of sensitive production process for a chemical plant of your organization. This project is severely budget constrained. One
of the units is located in a politically sensitive area and an unexpected disturbance has increased the project budget by 15%. What should be the risk
response strategy in this case?
Options:
A: Accept
B: Avoid
C: Expolit
D: Transfer
Answer is A, but my anser was D to transfer with an insurance.
as we can avoid political instability....is that correct?